Monday, September 24, 2012

September 24, 2012 - Taxiway F Open to Air Traffic

September 24, 2012 - Taxiway F Open to Air Traffic:

Today the construction on the Taxiway F crossing of Runway 1/19 was completed and the pavement was opened to air traffic.  The Taxiway B north and Lima were closed to complete the pavement marking and landscaping on Contract 1.
 

Wednesday, September 19, 2012

September 19, 2012 - Contract 2 Project Construction Starts

September 19, 2012 Construction on Contract 2 Begins:

The contractor began construction operations on the follow-up (Contract 2) contract for the rehabilitation of Runway 1/19.  Construction is expected to be completed by mid-November 2012.  The Runway 1/19 will be closed throughout this phase of construction. 

Construction work continued on the pavement marking for the Contract 1 project. 

Sunday, September 16, 2012

September 16, 2012 - RUNWAY INTERSECTION OPEN!!

Runway 1/19 and 7/25 Intersection Opened for Operations!!

After 43 days of major construction work, the Runway 1/19 and 7/25 intersection reconstruction is completed and open to air traffic.  Runway 7/25 has been restored to its FULL length.  Following the combined close coordination and excellent cooperation by all the people working to complete this challenging project, we have met the aggressive schedule on time.  CONGRATULATIONS to everyone associated with the effort.  THANK YOU to all the tenants and users of the airport for your patience during this major improvement to RFD. 

Full Length Operations Return on Runway 7/25


Work will continue over the next several weeks to complete Runway grooving, marking, PAPI installation and landscaping.  Various minor closures may be necessary to complete these items of work.

Saturday, September 15, 2012

September 15, 2012 - REMINDER: Runway 7/25 and 1/19 Closed Tonight

Reminder: Tonight Runway 7/25 and 1/19 will be Closed at 11:00 pm until Sunday, September 16, 2012 at 4:00 pm to remark and relight the Runway 7/25 Threshold to its Full length.  Following this work, Runway 7/25 will be available FULL length.

Thursday, September 13, 2012

September 13, 2012 - Contract 2 for Runway 1/19 Rehabilitation STARTS!

Contract 2 for Runway 1/19 Rehabilitation Started Today!

Work began this morning on the Contract 2 Rehabilitation project for Runway 1/19 this morning.  The contractor began pavement removal operations in preparation for concrete paving in the next few weeks.

Reminder: Runway 1/19 will remain closed until late November to complete this next phase of reconstruction.

Wednesday, September 12, 2012

September 12, 2012 - NOTICE of Runway 1/19 Full Closure!!

September 12, 2012 - NOTICE of Runway 1/19 FULL Closure for Contract 2 Construction Start:

The next contract to reconstruct Runway 1/19 will begin tomorrow morning at 5:30 am requiring the full closure of the Runway 1/19.

Due to funding limitations, the entire Runway 1/19 Reconstruction has been broken into multiple contracts or phases.  We will be completing the first critical phase of the reconstruction in the next few weeks.  The next contract (Contract 2) will begin with the removal of the existing pavement on the center portion of the runway (south of the Contract 1 portion just wrapping up this weekend).  The FULL length of Runway 7/25 will be available throughout the Contract 2 project this fall.  The airport was fortunate to receive funding for the next phase of work and therefore, the contractor is continuing south with the reconstruction effort.  Due to the reconstruction work being completed on the center portion of the runway, the remaining length of runway outside the work zone is not long enough to be useable.  Therefore, Runway 1/19 will remain closed during the duration of the work this fall.  The next Contract is scheduled to be completed by late November 2012. 

September 12, 2012 - Expedited Runway Intersection Paving Complete

September 12, 2012 - All Paving on Runway 1/19 and 7/25 Expedited Work Area Completed!

All paving work on the Runway Intersection is complete.  The contractor is continuing to work on ancillary work items such as, electrical lights and signage installation, shoulder grading and sanitary sewer abandonment. 

Finishing Bituminous Paving and Electrical Work

We are preparing for a weekend closure of Runway 7/25 to return the runway to its full length.  This closure will begin on Saturday, September 15, 2012 at 11:00 pm and end on Sunday, September 16, 2012 at 4:00 pm local time.