Friday, October 19, 2012

October 12, 2012 - Concrete Paving on Contract 2 Complete!

October 12, 2012 - Concrete Paving Complete on Contract 2:

The contractor completed the concrete paving on the second phase of the Rehabilitation project for Runway 1/19 today.  Work will continue next week with the Bituminous paving on the shoulders and installation of the underdrain system.

October 9, 2012 - Contract 1 Marking Complete

October 9, 2012 - Contract 1 Work is Substantially Complete!

The contractor completed pavement marking to substantially complete the work on the Contract 1 Rehabilitation project!  Minor landscaping and cleanup of the construction staging area will continue during the next few weeks.

Contract 2 work continues with concrete paving expected to be complete October 12th.

Notice of Weekend Closure!

October 6, 2012 and October 7, 2012 Weekend Closure:

Notice:  This weekend the Runway 7/25 and 1/19 will be closed from 11:00 pm on October 6th to 4:00 pm on October 7th.  The contractors work area impacts the Runway Safety Area and requires closure to complete the Runway 25 PAPI installation. 

Tuesday, October 16, 2012

October 16, 2012 - Underdrain Installation

October 16, 2012 - Underdrain System Installation:

The contractor started installing the underdrain system along the Runway 1/19 pavement on Contract 2 today.  We expect the underdrain system installation to be completed in approximately 10 days. 

Bituminous paving on the Runway shoulders will begin on October 29th.  We are still targeting project completion of the Runway 1/19 project by mid-November.

Monday, October 1, 2012

October 1, 2012 - Concrete Paving Begins on Contract 2

October 1, 2012 - Concrete Paving Begins on Contract 2:

Concrete Paving began on Contract 2 today.  Paving is expected to continue for the next 8 - 10 days.   
Phase 2 Concrete Paving