The contractor is progressing well on Phase 1 Construction. Due to the extreme heat concrete paving completion has been pushed back to Monday, July 9th. We anticipate an early phase change into Phase 2 due to excellent progress and great weather. We anticipate moving up the "bulls eye" construction and relocation of the Runway 25 threshold to the weekend of July 28th!! Stay tuned for more details and schedule information.
Concrete Paving for Phase 1 Nearly COMPLETE. |