Work continues on the critical "Bulls Eye" area of the project. The pavement removal subcontractor is making good progress removing the existing intersection pavement and expects to be completed by the end of the week.
Runway Intersection Pavement Removal Operations |
New Taxiway F edge lighting installation |
Preparation of In-Pavement Centerline Lighting |
With the new Relocated Threshold on Runway 25, airport operations have had little impact from construction operations.
Ryan Air Boeing 767 approaches the Airport over construction |
We expect new concrete paving to start on Tuesday, August 14, 2012.