Thursday, August 23, 2012

August 23, 2012 - Concrete Paving Progressing on Schedule

August 23, 2012 - Concrete Paving on the Expedited Intersection is Progressing On Schedule:

Concrete Paving operations are continuing to progress nicely on the Runway 1/19 and 7/25 Intersection area of the project.  Concrete paving operations are expected to be complete by next Friday, August 31, 2012.  Bituminous paving on the shoulders is expected to be started after the Labor Day weekend.

New Concrete Pavement on the Intersection of Runway 7/25 and 1/19 looking south
New Concrete Paving Runway 7/25 looking northwest