Tuesday, October 16, 2012

October 16, 2012 - Underdrain Installation

October 16, 2012 - Underdrain System Installation:

The contractor started installing the underdrain system along the Runway 1/19 pavement on Contract 2 today.  We expect the underdrain system installation to be completed in approximately 10 days. 

Bituminous paving on the Runway shoulders will begin on October 29th.  We are still targeting project completion of the Runway 1/19 project by mid-November.