September 12, 2012 - All Paving on Runway 1/19 and 7/25 Expedited Work Area Completed!

All paving work on the Runway Intersection is complete.  The contractor is continuing to work on ancillary work items such as, electrical lights and signage installation, shoulder grading and sanitary sewer abandonment. 

Finishing Bituminous Paving and Electrical Work

We are preparing for a weekend closure of Runway 7/25 to return the runway to its full length.  This closure will begin on Saturday, September 15, 2012 at 11:00 pm and end on Sunday, September 16, 2012 at 4:00 pm local time.