September 16, 2012 - RUNWAY INTERSECTION OPEN!!

Runway 1/19 and 7/25 Intersection Opened for Operations!!

After 43 days of major construction work, the Runway 1/19 and 7/25 intersection reconstruction is completed and open to air traffic.  Runway 7/25 has been restored to its FULL length.  Following the combined close coordination and excellent cooperation by all the people working to complete this challenging project, we have met the aggressive schedule on time.  CONGRATULATIONS to everyone associated with the effort.  THANK YOU to all the tenants and users of the airport for your patience during this major improvement to RFD. 

Full Length Operations Return on Runway 7/25


Work will continue over the next several weeks to complete Runway grooving, marking, PAPI installation and landscaping.  Various minor closures may be necessary to complete these items of work.